2560 Carmel Valley Rd, Del Mar. Structural steel per plan: quadruple moment frame, 5 moment connections w/ UT deputy weld tests; heavy W-sections (W16x77, W14x53 x6, W14x74, W12x65, W12x58 x2, W12x45 x2). Manpower (Ben 7/20): shop ~3 weeks / 2-3 welders; field 3-5 days / 2-3 welders + 2 helpers. For Ruckle Construction Inc. My part: project management at B&B Industrial Welding, Apr 2026 – Jul 2026.